Now that fewer vehicles are on the streets with summer underway for HPISD and SMU, work will begin on resurfacing streets with pavement that needs repair in University Park on May 31. Weather permitting, this effort will continue in numerous locations through mid-August. Crews will work Monday through Friday from 8 a.m. to 5 p.m. If weather causes project delays, some Saturday work may be authorized. When resurfacing occurs on non-residential streets, lanes may be narrowed and flag crews may be present. For most segments, the resurfacing effort will take less than two days.
Vehicles in front of homes
Streets will be closed while the mill and overlay work is taking place. The day before work begins, front door notices will be delivered reminding residents not to park in front of their homes on the dates indicated. City staff will also place “No Parking” signs along the street the day before milling and overlay work occurs. Any vehicles parked on the street on the days milling and asphalt overlay are scheduled will be towed at the owner’s expense. Although unlikely, if for some reason work is not completed on the scheduled day, “No Parking” signs will remain in place.
Resurfacing Locations
The list of resurfacing locations for the first half of June is below. Progress will be updated throughout the project. As the project progresses, resurfacing locations for the later half of June and July will be added. Residents are encouraged to follow the City’s social media platforms and refer to the City’s website for the latest project information and related traffic advisories. Thank you for your patience and understanding as this necessary work takes place. Your tires will be happy once the project is complete!
Street | Milling Date | Progress | Repaving Date | Progress |
---|
Daniel from Willard to Cleburne | 5/31/23 | Completed | 6/2/23 | Completed |
Fondren from Boedeker to Dublin | 5/31/23 | Completed | 6/2/23 | Completed |
Dublin from McFarlin to University | 5/31/23 | Completed | 6/2/23 | Completed |
Milton from Cleburne to Dublin | 6/1/23 | Completed | 6/6/23 | Scheduled |
Dublin from Rosedale to Lovers | 6/1/23 | Completed | 6/6/23 | Scheduled |
Durham from Rosedale to Lovers | 6/1/23 | Completed | 6/7/23 | Scheduled |
Westminster from Durham to Airline | 6/2/23 | Completed | 6/7/23 | Scheduled |
Rankin from Hillcrest to Airline | 6/2/23 | Completed | 6/7/23 | Scheduled |
Milton from Airline to Athens | 6/5/23 | Completed | 6/7/23 | Scheduled
|
Rosedale from Hillcrest to Airline | 6/5/23 | Completed | 6/7/23 | Scheduled
|
Daniel from Hillcrest to Airline | 6/5/23 | Completed | 6/12/23 | Scheduled
|
McFarlin from Hillcrest to Dickens | 6/6/23 | Scheduled | 6/13/23 | Scheduled
|
Dickens from McFarlin to Haynie | 6/6/23 | Scheduled | 6/14/23 | Scheduled
|
Granada from Hillcrest to Key | 6/6/23 | Scheduled | 6/15/23 | Scheduled
|
Thackery from McFarlin to Rosedale | 6/6/23 | Scheduled | 6/16/23 | Scheduled
|
Rosedale from Thackery to Golf | 6/8/23 | Scheduled | 6/19/23 | Scheduled
|
Milton from Thackery to Golf | 6/9/23 | Scheduled | 6/19/23 | Scheduled
|
McFarlin from Golf to Williams | 6/9/23 | Scheduled | 6/20/23 | Scheduled |
McFarlin from Park to Shannon | 6/9/23 | Scheduled | 6/20/23 | Scheduled
|
Hunters Glen from University to Turtle Creek | 6/12/23 | Scheduled | 6/21/23 | Scheduled
|
Saint Andrews from Westwick to Connerly | 6/13/23 | Scheduled | 6/22/23 | Scheduled
|
San Carlos from Preston to Douglas | 6/13/23 | Scheduled | 6/22/23 | Scheduled
|
Normandy from Preston to Douglas | 6/13/23 | Scheduled | 6/23/23 | Scheduled
|
Potomac from Armstrong to Lomo Alto | 6/13/23 | Scheduled | 6/23/23 | Scheduled
|
Armstrong from San Carlos to University | 6/14/23 | Scheduled | 6/26/23 | Scheduled
|
Stanhope from Lomo Alto to Roland | 6/15/23 | Scheduled | 6/29/23 | Scheduled
|
University from Armstrong to DNT | 6/15/23 | Scheduled | 6/30/23 | Scheduled
|
Lomo Alto from University to Emerson | 6/16/23 | Scheduled | 7/3/23 | Scheduled
|
Emerson from Lomo Alto to DNT | 6/16/23 | Scheduled | 7/3/23 | Scheduled
|
Westchester from McFarlin to Emerson | 6/16/23 | Scheduled | 7/5/23 | Scheduled
|